Advertised Projects
Check out Toho's Procurement Portal for all the projects we have advertised. Once registering on the portal, you can make your submissions.
Forecasted Projects
Below is a list of our forecasted engineering projects.
Project Name / Description | Project Type | Anticipated Advertise Date | Approximate | Grant | Estimated Date to Start Construction | Estimated Project Duration |
|---|---|---|---|---|---|---|
16-inch FM Simpson Road to Parkway WRF CIP-1070: A proposed 16" force main from Simpson Road to Parkway WRF to coincide with the Parkway WRF expansion project. Also, this project will grout and abandon in-place an existing 12" ACP FM. | IFB (Contractor) | November 2026 | $3.5-4M | N | April 2027 | 18 months |
Osceola Polk Line Rd - TWA Southwest WTP east to South Nocatee Road (US17-92 from CR532 to Nocatee Road) - WIFIA Funded CIP-1059: Installation of 30-inch transmission waterline along Route 17-92 (South Orange Blossom Trail) from Osceola Old Polk Line Road (CR 532) to Nocatee Street in Intercession City. | IFB (Contractor)) | November 2026 | $10-12M | Y | January 2027 | 18 months |
Hoagland Blvd. 20" Water Main Extension - WIFIA Funded CIP-0961: This project is identified in the Master Hydraulic Model updates. This project is anticipated to increase water supply service by approximately 1.29 MGD to the Poinciana service area. The 24" water main is required to transfer potable water from the Toho area to the Poinciana area to meet distribution system demands. This project includes a 24" water transmission main to run from the future Plant just north of Pleasant Hill Elementary School and south of Clay St. The 24" water main will generally be installed west of the start location along the access road north of the elementary school, south along Jack Calhoun Dr. and South Hoagland Blvd, and through Good Samaritan Village. | IFB (Contractor) | November 2026 | $9M | Y | February 2027 | 18 months |
Multiple Facility Development Projects and Land Acquisition Assistance CIP-0975: Toho has identified through a 'Facilities Master Plan' several larger projects that include new office building(s), warehouse, additional storage, parking, etc. and is requesting qualifications from firms with land development design, permitting, planning, architectural, and construction oversight experience to assist Toho in these planned facility projects. Toho will also seek assistance with right-of-way, easement, and land acquisition services through this solicitation. | RFQu | November 2026 | N/A | N | N/A (ongoing) | Continuous |
SSWRF Reuse Storage Pond Expansion - HUD and WIFIA FUNDED CIP-0977: Approx. 26 MG expansion of the existing reuse storage pond. | IFB (Contractor) | November 2026 | $6.2M | Y | February 2027 | 12 months |
Reaves Road FM Replacement - HUD Funded CIP-1024: Reports from Asset Management indicate that 11 total breaks occurred on the 6” Fusible PVC FM from LS 148 to Pleasant Hill Rd/Reaves Rd intersection. The FM is currently out of service and a temporary FM has been installed from LS-148 to a terminal MH located in Reedy Reserve Phase 2. The current Evergreen‐Reaves Rd FM route from LS‐148P is approximately 7200 ft long culminating and tying into an eight‐inch force main that manifolds with additional lift stations downstream from the connection. The goal of this project is to reroute the flow to the Poinciana system by installing approximately 4000 ft of 4‐inch HDPE force main, if possible. | IFB (Contractor) | November 2026 | $2M | Y | January 2027 | 12 months |
Cypress Lake WTP to Southport Road Water Transmission Main Project (Segment CL2-P-01A) CIP-1104: Approximately 41,500 linear feet of a new 36-inch potable water transmission main from Cypress Lake WTP along utility easements, future Southport Connector, Southport Canal and connecting to a new 36-inch water transmission main project at Southport Road. | Pre-qualification contractors for large diameter transmission main | November 2026 | $45-$50M | Y | November 2027 | 20 months |
Southport Road Water Transmission Main Project (Segment CL2-P-02A) CIP-1112: Approximately 32,000 linear feet of a new 36-inch potable water transmission main from Southport Canal to the intersection of Poinciana Blvd. and Pleasant Hill Road. | Pre-qualification contractors for large diameter transmission main | November 2026 | $45-$50M | Y | August 2027 | 21 months |
Reuse Main Extension from Kindred to NeoCity in Osceola County, Florida CIP-1000: 19,000 LF of 20" reuse main including open cut, HDD, and aerial segments. | IFB (Contractor) | December 2026 | $11M | N | December 2026 | 12 months |
Sunbridge WRF Expansion to 3.5 MGD CIP-0600: Water Reclamtion Facility Expansion from 1.0 MGD to 3.5 MGD includes Site Work, Yard Piping, Pretreatment Structure, Odor Control, Process basin improvements, Aeration Blowers, RAS/WAS Pump Station, Sodium Hypochlorite with Pavillion, Disk Filters, Chorine Contact Chamber, Reclaimed Water Pump Station, Sludge Holding Tanks, Maintenance and Storage Facility, Alum Storage & Feed, SCADA & Fiber Ring, Electrical I&C. | CMAR | December 2026 | $50-60M | N | July 2027 | 24 months |
Continuing Geotechnical, Environmental, and Materials Testing Services: Seeking qualified firms with demonstrated experience in geotechnical engineering, environmental services, construction materials testing, and related technical support. Services may include, but are not limited to:
| RFQu | January 2027 | ||||
Continuing Surveying, Subsurface Utility Engineering (SUE), and Right-of-Way (ROW) Mapping Services: Seeking qualified firms with demonstrated experience in land surveying, utility mapping, right-of-way services, and subsurface utility engineering. Services may include, but are not limited to:
| RFQu | January 2027 |