Advertised Projects

Check out Toho's Procurement Portal for all the projects we have advertised. Once registering on the portal, you can make your submissions. 

Advertised Projects
Image of reuse facility expansion.

Forecasted Projects

Below is a list of our forecasted engineering projects

PROJECT NAME/ DESCRIPTIONTYPEANTICIPATED ADVERTISE DATEAPPROXIMATE BUDGETGRANT
(Y/N)
ESTIMATED CONSTRUCTION DATE STARTESTIMATED PROJECT DURATION
Hoagland Blvd. 20" Water Main Extension CIP-0961: This project is identified in the Master Hydraulic Model updates.  This project is anticipated to increase water supply service by approximately 1.29 MGD to the Poinciana service area.  The 24" water main is required to transfer potable water from the Toho area to the Poinciana area to meet distribution system demands.  This project includes a 24" water transmission main to run from the future Plant just north of Pleasant Hill Elementary School and south of Clay St.  The 24" water main will generally be installed west of the start location along the access road north of the elementary school, south along Jack Calhoun Dr. and South Hoagland Blvd, and through Good Samaritan Village.RFQuMay 2025$9MNJuly 202518 months
Parkway WRF Expansion to 2.0 MGD CIP 1012: CMAR Construction for interim expansion from 1.5 MGD to 2.0 MGD. The improvements include new pretreatment units for screening, two new clarifiers, a new pump station to return sludge, re-lining of reject pond, reconstructing the chlorine contact chamber and renovation of operations building, pavement and ADA ramp.RFQu (CMAR)May 2025$20-25MSeptember 202514 months
South Poinciana Blvd from Crescent Lakes Way to OBT CIP-1148: Cypress Lake Transmission Main (Segment CL2-P-04B) approximately 12,500 LF of parallel 30" pipe along South Poinciana Blvd from Crescent Lakes Way to South Orange Blossom Trail.  The project includes route analysis, preliminary design, surveying and SUE services, geotechnical investigations, roadway project coordination, permitting, and bidding assistance, final design, and construction administration services.  This project is located along a major arterial road which may include a high maintenance of traffic (MOT) plan.  RFQu (Engineer)May 2025$12MNFebruary 202724 months
Financial Institution Procurement for Letter of Credit for WCCFRFP (Financial)June 2025N/ANN/AN/A
Mann St. Toho Utilities Relocation: City of Kissimmee has a project to perform road widening and improvements of Mann St, in Kissimmee. This project will impact some existing TWA utilities, which will need to be relocated before the roadway project. IFB  (Contractor)June 2025400KNAugust 20254 months
Harmony WRF 2.0 MGD Expansion - CIP-0614: The project will expand the Harmony WRF from 0.75 MGD to 2 MGD.RFQu (CMAR)June 2025$50MNMid-202624 months
Northwest WTP Storage Expansion CIP-0999: Construction of a new 1.0 MG ground storage tank and associated piping, a new above grade metering station and required stormwater improvementsIFB (Contractor)July 2025$6.5MNSeptember 202514 months
Sunbridge WRF Expansion to 3.5 MGD: CMAR Construction for WRF expansion.  The improvements include new pretreatment units, treatment process expansion, a new in-plant pump station, effluent transfer pumps, reclaimed water high speed service pumps, new chlorine contact chamber and biosolids and dewatering system improvements.RFQu (CMAR)July 2025$35MNJune 202618 months
CL1-P-01 Old Pleasant Hill Rd/Dover Plum Ave. S. Poinciana Blvd. to Country Club Road CIP-1028: This project includes the addition of approximately 6,500 LF of 20" water main. The proposed connection points for the new main are: 1) the 24" water main located approximately 500' west of the intersection of Pleasant Hill Rd and South DoverPlum Ave. and 2) the 12" water main located at the intersection of Cypress Parkway and Marigold Ave. Toho is applying for WIFIA funds for this project. Advertisement is anticipated for Spring 2025.IFB (Contractor)July 2025$5.5MNOctober 202518 months
St. Cloud Downtown WM Replacement CIP-0627: The potable water infrastructure in St. Cloud’s downtown area includes one-inch diameter galvanized steel pipe (GSP) and four and six-inch cast iron pipe (CIP), materials that are no longer used by Toho in distribution system construction and are also undersized. These mains have a greater probability of failure and can contribute to pressure issues. To address these concerns, this project will replace and upsize infrastructure at four locations in the downtown St. Cloud area.IFB(Contractor)August 2025$2.4MYDecember 20256 months
St. Cloud LS Diversions CIP 1008: St. Cloud’s LS 40 has reached capacity. In response to this problem, Toho has worked with a developer to construct a 16”/20”/24” Kissimmee Park FM spanning approximately 19,000 LF and divert existing Toho East LS connected to LS40 to the Kissimmee Park FM. Plans for this force main have been completed and awaiting bid. The plans include the stub outs and diversions.IFB(Contractor)August 2025$1.88MNNovember 202512 months
Richard McLaughlin (NB) WRF Valve Replacement CIP-0980: Replace one 48” and two 36” isolation valves, one 30” and one 36” flow meter isolation valve, and one 36” flow meter bypass valve. Project also includes installation of a 20” bypass line, magnetic flow meter, and the replacement of the radio tower, and plant security system upgrade.IFB  (Contractor)August 2025$3M to $4.0MNOctober 2025 
Lake Marion WRF AWT Improvements CIP-0658: The project upgrades the Lake Marion WRF to reduce effluent Total Nitrogen and Total Phosphorus limits.  The project also includes treatment component improvements to maintain the facility and improve operational efficiency.RFQu (CMAR)September 2025$27MTBDMid-202624 months
OUC Interconnect CIP-0664: Toho and OUC are considering potential potable water interconnections between the two utilities. Toho and OUC agreed to initiate hydraulic evaluations to determine how best to implement the interconnects and how much water could be delivered through the interconnects from OUC to Toho and from Toho to OUC. In parallel, Toho and OUC are working on the details of a potential agreement. Interconnect 1: extends approximately 380 feet south from OUC’s 16-inch water main on Golden Sunburst Avenue to the existing Toho 24” water main on Boggy Creek Road. Interconnect 2: Toho (Simpson Road) and OUC (Boggy Creek Road) systems are approximately 500 feet between the 16” Toho and 12” OUC water mains. IFB(Contractor)November 2025$3.8MNJanuary 20266 months
Toho Small Projects CIP-1115: this is a batch of small projects around the Toho service area. They include a 1200 LF WM extension along Carol Terrace, a 500 LF WM extension on Patricia Circle, three interconnections at Sherwood Forrest, Celebration, and KOA/Monterrey, service line replacements at Grand Palms, and installation of a driveway at the Reunion Reuse Station.IFB(Contractor)December 2025$3MNTBD8 months
16" RM Old Hickory Tree Rd/10th Street/Narcoossee Rd CIP-0990: Supplement growth in the northeast service area by extending a sixteen-inch reclaimed main along Old Hickory Tree Rd to E 10th Street, east to Narcoossee Rd for a total length of approx. 12,000 feet.IFB (Contractor)December 2025$6 millionYMarch 20261 year
Friar's Cove Water Main CIP-0979: 19,900 LF of 24" water main along east side of Lake Tohopekaliga.  Includes two turnpike crossings and connection to existing watermains.IFB  (Contractor)June 2026$7.3 millionNSeptember 202618 months