Projects
Sewer system preventive maintenance night monitoring
As part of preventative maintenance, Toho has contracted with USSI LLC to identify leaks, defects and stormwater inflows in Toho’s sewer system. Starting the week of February 16-20 and March 2-6, USSI personnel will be conducting night monitoring between the hours of 11 p.m. and 5:30 a.m. Schedules may vary due to weather and unforeseen circumstances. Please see map below.
Solivita community backflow replacement project
02.16.26 - The backflow replacement project in Solivita has been paused to repair the backflows that were affected by the recent extreme cold weather in Toho’s service area. The replacement activities are expected to resume in the next month or so and should be completed in a few months. Schedules may change due to weather and unforeseen circumstances.
###
Sewer smoke tests
Toho has contracted with USSI LLC to conduct smoke tests on the sewer infrastructure in the service area. This safe preventative maintenance test will help identify leaks, defects and stormwater inflows in Toho’s sewer system, thereby improving wastewater treatment operations and efficiency. Please see more details below.
Hickory Tree Road area water line installation project
Toho is announcing a water line installation project along Hickory Tree Road between Nolte Road and US 192 (please see map below).
The project is scheduled to get underway in early September and is expected to be completed by June 2026 along with area restoration. Work will take place Monday-Friday from 7 a.m. to 6 p.m. Schedules could vary according to weather and other unforeseen circumstances.
Marigold Avenue new sewer line project
12.23.25 - Due to a conflicting utility line discovered in the area, the installation method for the new sewer line needs to be revised. The revised installation method is still anticipated to utilize trenchless construction to minimize impact to the area and traffic. A timeline for the revised project is expected to be finalized in the new year.
###
Majestic Oaks survey activities
Toho Water Authority has selected consultant Dewberry Engineers, Inc. to begin planning the replacement of the current 4-inch water line with a larger 6- or 8-inch line. This upgrade will enhance water service and provide improved fire protection for the Majestic Oaks community.
Buenaventura Lakes water treatment facility upgrades
The Buenaventura Lakes water treatment facility is currently being upgraded to improve the long-term operations of the facility and enhance water quality. Improvements will also be made to reduce flooding at the facility caused by heavy rains.
The project is expected to be completed by the fall of 2026. Most work takes place during normal working hours, Monday through Friday from 8 a.m. to 5 p.m. There may be instances of night-time work. Schedules could change due to weather and unforeseen circumstances.
The Oaks subdivision sewer improvements project
Toho Water Authority (Toho) is performing critical improvements to the sewer system in The Oaks subdivision. These infrastructure upgrades are essential to maintaining reliable wastewater service in your community.
The improvements are underway and are expected to be completed by the end of November 2025 along with area restoration. Schedules may change to weather and unforeseen circumstances. Please see tentative schedule and details below.
Lavon and Palm Avenue water line project
02.06.26 - The project is nearing completion. Area restoration is expected to get underway mid-February and be completed by the beginning of March.
###
Shingle Creek surface water treatment facility project
The Shingle Creek Surface Water Treatment Facility project will utilize water from Shingle Creek and treat it to drinking water standards. Once completed, the facility will have the capacity to treat six million gallons per day. The preliminary design including the pilot study of the treatment processes for the facility has been completed. Final design and permitting of the facility will start in the near future. The facility is expected to be operational by early 2027.